logo3

I&D/STP works under Namami Gange

Print

 

Sl Name of project Completion Period (AA&ES) Sanctioned Cost (Rs. In Cr.) Funds Released Expenditure As per bid
            Date of start Date of Completion As per CB / Expected
01 Upgradation of 3.50 MLD STP, Tapovan 9 Months(Dec.-2017) 2.19 0.62 0.59 15-09-17 14/03/18 - 28/02/18
2(a) I&D Part –II Sarai, Haridwar 24 Months(March-2019) 31.46 10.19 10.19 25-08-17 24/02/19 - 31/12/18
2(b) I&D Part -I Jagjeetpur, Haridwar * 30 Months(Sep.-2019) 84.82 9.96 9.96 23-09-17 22/09/19 - 22/03/19
03 I&D with STP, Kirtinagar, Tehri STP#1- 0.050ML STP#2 - 0.010 MLD 12 Months (March-2018) 4.23 0.71 0.46 15-09-17 14/03/18 - 14/04/18
04 I&D With STP, Badrinath *STP#1- 1.00MLD STP#2 - 0.010 MLD 24 Months(March-2019) 18.24 0.11 0.11 20-11-17 19/05/19 - 30/11/18
05 I&D With STP, Gopeshwar - STP#1- 0.76 MLD - STP#2- 1.19 MLD - STP#3- 1.25 MLD - STP#4- 1.12 MLD - STP#5- 0.05 MLD 18 Months (Sep-2018) 61.83 3.07 3.07 20-11-17 19/02/19 - 19/01/19
06 I&D With STP, Nandprayag STP#1- 0.05 MLD STP#2- 0.05 MLD STP#3- 0.05 MLD 15 Months(June-2018) 6.46 0.28 0.28 20-11-17 19/08/18 - 19/08/18
07 I&D with STP, Karanprayag STP#1- 0.05 MLD STP#2- 0.10 MLD STP#3- 0.05 MLD STP#4- 0.05 MLD STP#5- 0.10 MLD 18 Months(Sep-2018) 12.09 0.76 0.76 20-11-17 19/08/18 - 19/08/18
08 I&D with STP, Rudraprayag STP#1- 0.075 MLD STP#2- 0.10 MLD STP#3- 0.075 MLD STP#4- 0.10 MLD STP#5- 0.125 MLD STP#6- 0.05 MLD 18 Months(Sep-2018) 13.15 0.90 0.90 20-11-17 19/02/19 - 31/12/18
09 Upgradation of 2.0 Mld STP, Gyansu, Uttarkashi 24 Months (March-2019) 10.03 0.06 0.06 10-12-17 10/12/2018 - 10/11/2018
10 (a) Upgradation of 27 Mld STP, Jagjeetpur, Haridwar 18 Months (Sep-2018) 19.65 0.27 0.27 01-12-17 28/02/2019 - 31/12/2018
10 (b) Upgradation of 18 Mld STP, Sarai , Haridwar 18 Months (Sep-2018) 12.99 0.27 0.27 01-12-17 28/02/2019 - 31/12/2018
11 Upgradation of 3 MLD STP, Swargashram 12 Months (March-2018) 5.20 0.05 0.00 01/01/18 30/06/2018 - 30/05/2018