River Front Development works under Namami Gange

Print

 

Sl Name of project Completion Period (AA&ES) Sanctioned Cost (Rs. In Cr.) Funds Released Expenditure As per bid
            Date of start Date of Completion As per CB / Expected
01 Upgradation of 3.50 MLD STP, Tapovan 9 Months(Dec.-2017) 2.19 0.62 0.59 15-09-17 14/03/18 - 28/02/18
2(a) I&D Part –II Sarai, Haridwar 24 Months(March-2019) 31.46 10.19 10.19 25-08-17 24/02/19 - 31/12/18
2(b) I&D Part -I Jagjeetpur, Haridwar * 30 Months(Sep.-2019) 84.82 9.96 9.96 23-09-17 22/09/19 - 22/03/19
03 I&D with STP, Kirtinagar, Tehri STP#1- 0.050ML STP#2 - 0.010 MLD 12 Months (March-2018) 4.23 0.71 0.46 15-09-17 14/03/18 - 14/04/18
04 I&D With STP, Badrinath *STP#1- 1.00MLD STP#2 - 0.010 MLD 24 Months(March-2019) 18.24 0.11 0.11 20-11-17 19/05/19 - 30/11/18